Doug the digger was out at The Dig with his team, rough grading the lot; I stopped in around 5pm, they look to be half-way done. Doug did save my rock collection, too. Doug started pumping the water out of the basement but looks to be only a foot or so lower. Hope they finish that tomorrow.

Rod also called earlier today, he gave me the plan for this week. Sounds like rough grade Monday & Tuesday, then the steel beams on Wednesday, and then the start of framing on Friday or next Monday. Coooool! This is where it begins to look like a house.

I also called the two deck builders, asking for a confirmation on them receiving my info successfully. Brew City did call back. Have yet to hear from the other dude.